TransAlta has gained backing for its proposed 150-megawatt Mt Keith gas power plant, but it is unclear when the project will proceed, given the shutdown of BHP's nickel operations.
The shutdown of BHP's nickel operations has had a silver lining for Kalgoorlie, with Canadian company TransAlta contracted to supply back-up power to the city.
The fallout from BHP mothballing its Nickel West operations has had a ripple effect through engineering and haulage contractors, fellow miners, airlines and power suppliers.
Canadian firm TransAlta is seeking environmental approvals for a 150-megawatt gas-fuelled power station to support processing at BHP Nickel West's Mount Keith operations.
The power plant that supported Kalgoorlie during last week's power outage was, in 2023, rejected by the state government in favour of its own facility, which tripped when it was needed.
Indigenous contractor Cundaline has secured work on a major solar and battery project in the Northern Goldfields to power BHP's nickel mining operations.
TransAlta will build a $73 million solar and battery project in the Northern Goldfields to power BHP Nickel West, helping the miner cut carbon for battery products.
In an initiative led by the Chamber of Minerals and Energy of WA, the Western Australian resources sector has pledged $6.6 million to Royal Flying Doctor Service Western Operations, Foodbank WA and Lifeline WA.
Fortescue Metals Group has failed to get its hands on a crucial engineering report at the heart of a legal dispute with Canadian company TransAlta Corporation.
Iron ore miner Roy Hill has connected its Port Hedland operations to Horizon Power's North West Interconnected System following the installation of extensive underground facilities, which began in 2016.
TransAlta officially opened its new 150-megawatt combined cycle natural gas power station in South Hedland today, with Horizon Power as its sole foundation customer after Fortescue Metals Group backed out of an offtake agreement.
Fortescue Metals Group has terminated its agreement with TransAlta Corporation to purchase power from the recently completed South Headland power station after the miner raised performance concerns in August.
Fortescue Metals Group claimed today that a new power station built by Canadian company TransAlta Corporation at South Hedland had failed to achieve commercial production, while the miner also announced it would buy back a second power station it sold to TransAlta in 2012.
Commissioning has been completed today at a 150-megawatt gas power station in South Hedland built by Canadian energy company TransAlta, to power Horizon Power customers and Fortescue Metals Group's operations.
TransAlta Corporation has had a small win in the Supreme Court after successfully defending an entitlements claim by Monadelphous Group, but the engineering firm is still pursuing about $33 million from a joint venture comprising a Pilbara-based subsidiary of the Canadian power utility and DPB Development Group.
The new owners of Quadrant Energy have spoken to Business News about how the $2.7 billion acquisition came together and their plans for the oil and gas producer.
In some of the state's more remote towns, where electricity can be 700 per cent more expensive to deliver than in Perth, embracing cheaper new technology is only part of the solution to driving down costs.
Energy utility owner Duet Group is set to become a bigger player in the WA market, after announcing an agreed $1.4 billion takeover of remote power producer Energy Developments.
A 270 kilometre-long gas pipeline connecting Fortescue Metals Group's Solomon hub operations to the Dampier natural gas pipeline was officially opened today.
Asset sales, cost cutting and restructuring are under way across WA, creating opportunities for professional services firms. Click through to see details of more than 30 privatisation deals in WA, from 1961 to the present day.
A dispute between privately owned Alinta Energy and Horizon Power hangs over state government plans to overhaul the north-west's unregulated electricity network.
The private developer of a 150 megawatt power station with contracts to Fortescue Metals Group has announced the all inclusive cost of the project will be $570 million.
SPECIAL REPORT: With new project work from the resources and government sectors slowing down, contractors will need to look harder for work opportunities.
The state government has secured private funding to build own and operate a 150 megawatt power station in South Hedland which will incorporate infrastructure from a smaller power station that collapsed engineering company Forge Group was building.