Pilot flicks switch on data centre at WA oil and gas site

Just in

Bookmark

Save articles for future reference.

Pilot Energy has commissioned the first module of its Dongara data centre at the Cliff Head plant site near Dongara in Western Australia, marking a significant step in the company’s diversification from oil and gas into high-performance computing. Delivered on schedule and within budget with UAE-based partner Kala Data, the initial 0.4MW of computing capacity is now live, with three additional 1MW modules planned for the second half of 2026 to take total capacity to 4MW.